Thread: [Solved] Predecessor not considered?
View Single Post
 
Old 09-08-2014, 02:57 AM
Puddlerunna Puddlerunna is offline Windows Vista Office 2010 32bit
Novice
 
Join Date: Sep 2014
Posts: 17
Puddlerunna is on a distinguished road
Default

Hi Julie,

See attached file.
The area I keep having problems with is the Summary Task "Design" and all its subtasks.
Despite the "Schedule from Project End Date", the tasks need to start as soon as possible, on or after 25.08.
The project is purely milestone driven, duration is not driving in this case.

I figured giving Line 3 a Start No Later than 25.08. constraint and Line 5 a "3SS" dependency would do the trick, but it won't.

Maybe I'm missing something fundamentally, but I got it to work before (see attached screenshot).
Line 3 has a SNLT constraint of 25.08. and all others seemingly fall into line with a ASAP constraint.
Attached Images
File Type: jpg Project_Template.jpg (110.4 KB, 14 views)
Attached Files
File Type: zip Project_Template.zip (70.2 KB, 8 views)