Modelling training modules
Hi,
I am new to MS Project so this might be a very simple question.
I have a number of training modules to organise, each comprising a different number of training days and a different number of attendees.
I guess MS Project can help me model the different options available to me (put less/more training staff on one module to prolong/reduce total training time, and see the effect in real time).
So for instance, if a particular training module requires 2 groups of people to attend a 10-hour session, I can either put 1 trainer for 2x10 hours or 2 trainers for 1x10 hours each, thus halving total training time.
How can I do that in MS Project so I can have different scenarios to show to my managers?
Thank you so much
|