Project has always assigned resources at his/her max units (assuming max units of 100% or less).
If you want to shut off resource leveling, check Leveling Options on the Resource ribbon and ensure it is set to Manual.
The other options is to set the resource's max units to a high value (500% or what ever is needed) to stop Project from flagging a resource as overallocated.
|