why am i able to enter data into baseline
View Single Post
08-22-2014, 06:51 AM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
Project does not prevent baseline data from being manually changed. Only if using Project Server, can you "lock" baselines.