Hi Julie

I think I am confusing myself!

Basically I have multiple resources assigned to the same tasks throughout my schedule. I have levelled the schedule and here lies the issue. There are often instances where a resource will not have any work loaded for them for a long period, because they are waiting for another/other resources to become available before they can move on to the next task.

There are also lots of days where they are working but not being fully utilised too.

Is this simply because we have too many resources assigned to the same tasks and there is no way around the issues we are finding?

Can you offer a solution that doesn't involve creating the same task 4 times (if 4 people are working on it at the same time) and assigning them all individually to the duplicated tasks? the schedule will be so long if I have to do this.

Any help you can offer would be much appreciated

Thanks

Jo