Quote:
Originally Posted by JulieS
You are working with Manually scheduled tasks. Set the task to Autoscheduled and you'll be able to add Actual Overtime work.
|
Okay I unticked the Manually Scheduled checkbox and is able to add Actual Overtime Work. But now I'm confused:
Ovt. Work is 5h,
Baseline Work is 8h,
Why is the Actual Work is 12h, not 13h?
Is the formula for Actual Work = Baseline Work + Overtime Work? Or am I missing something?
I am very sorry for asking very basic questions, but as I mentioned before, I am really new at using MS Project.