View Single Post
 
Old 08-15-2014, 06:39 AM
JulieS JulieS is offline Windows 7 64bit Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm afraid this isn't possible. The Work field in a task view shows total work on the task - not broken down by each resource assigned. The Task Usage view is the best view to show each task and the assignment of each resource to the task.
Reply With Quote