Thread
: [Solved]
Showing reosurce and work in same field
View Single Post
08-15-2014, 06:39 AM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
I'm afraid this isn't possible. The Work field in a task view shows total work on the task - not broken down by each resource assigned. The Task Usage view is the best view to show each task and the assignment of each resource to the task.