Default Resource not getting enough hours allocated to them, therefore extending duration

Hi

I have a base calendar of 8 hours per day.

Example:

I have Bob who has a resource calendar of 6 hours per day.
Joe has a resource calendar of 4 hours per day.

I assign them both to a 40 hour task as follows:

Bob at 80%, and Joe at 20%.

Why is the duration calculating 7.38 days?

Additionally when I go into the resource usage view, it shows the following that joe is only being allocated 0.8 work per day. This is extending the duration. Further more the dates are 31/07/14 - 13/08/14. This is not 7.38 days??!!

Please help!

Thanks

jo