Resource not getting enough hours allocated to them, therefore extending duration
Hi
I have a base calendar of 8 hours per day.
Example:
I have Bob who has a resource calendar of 6 hours per day.
Joe has a resource calendar of 4 hours per day.
I assign them both to a 40 hour task as follows:
Bob at 80%, and Joe at 20%.
Why is the duration calculating 7.38 days?
Additionally when I go into the resource usage view, it shows the following that joe is only being allocated 0.8 work per day. This is extending the duration. Further more the dates are 31/07/14 - 13/08/14. This is not 7.38 days??!!
Please help!
Thanks
jo
|