Good points, Guloluseus. I agree that setting the dependencies is one way of solving the issue as well. The problem that I frequently see, however, is if there are truly no relationships between the tasks and you've imposed an order by linking F to S, resources frequently perform the tasks out of order. That can cause additional work to remove dependencies and set the correct Actual Start. I agree 100% with having the ability to show where overages come from - can still be done with my suggestion, as long as a baseline is saved.
|