Default

Yeah, its a bit annoying that it wont change over.
Can mark this as a solved as we have resorted to a workaround- the client has been given resource graphs for each labour group, which DO show labour in days. Given that this covers the contract requirements, fairly confident that this will work out.

the original programme was written in Primavera P6 (which I am learnig to loathe day by day) and after trying to produce reports in that I resorted to converting to Project and extracting info from there. At least Project will let you do that easily