i split the windo from view and then clicking on details. on the upper side i have the gantt chart. on the lower side i like to see something similar to task information but it is not visible. i want to see predecessor and successor of the task at least, that i click above in the gantt chart, in the window below. how can i do that?
Click in the Task Form (lower part of split) right click to show the shortcut Format menu and choose Predecessors and Successors. You can also show the Relationship Diagram view in the lower pane.

Quote:
or my goal is when i click on a task in gannt chart i want to see immediately its both predecessor and successor too. how can i do that?he task inspection oinly shows predecessor name and not succesor. i like to see successor too. if this is not possible at least how can i jump to a task? lets say a tasks successor is seen as task number 202 for example. how can i immediately jump to task 202 instead of scrollling?
F5 with task ID is the best option.