Hi Julie,
I cannot select Assignment as field type for task summary name, only resource. It is greyed out.
Any idea?
Any setup wrong?
Thanks
Bumpui
Quote:
Originally Posted by JulieS
The screen shot from above I believe is exactly what you need to do.
- Apply the Resource Usage view.
- Click the View Ribbon.
- Click the Group drop down.
- Select New Group.
- Create the group as I have shown in the screen shot.
|