Recurring tasks are grouped together under a summary task, so each of the occurrences of your Monday tasks would appear grouped underneath that summary.
When you define the recurring task, you set the range of recurrence from Start to Finish and each occurrence will be constrained with a Start No Earlier Than constraint. If a single occurrence has a predecessor it will obey the predecessor and the constraint - however - no other occurrences will be rescheduled.
I suggest creating some recurring tasks to better understand how they function.
|