Thread: [Solved] recurring tasks
View Single Post
 
Old 06-16-2014, 01:00 PM
JulieS JulieS is offline Windows 7 64bit Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Yes, the task is included in schedule calculation but recurring tasks are constrained with SNET constraints. You certainly may add predecessors and successors but assuming the tasks are shorter than the total duration, they will not increase overall project duration. If you assign resources, those assignments will be included in total work, total cost, and also used for resource overallocation.
Reply With Quote