Default physical complete %, regular work, vs % complete

in my schedule i was updating everything by % complete. now that i am near the end of the project almost everything is 100% complete in % complete columns. but when i checked physical % complete i saw that all are 0. "regular work" column also shows 0 for all. why is this the case?