Gotcha.
In the meantime I had generated a "behind schedule" filter instead, that fit my requirements. I suppose I could just use that going forward, since the tasks are not updated based on status date (currently). It's a very simple filter- just set it up to tell me the tasks that are past their expected finish date, and are less than 100% complete.
Thanks for the explanation.
E