Hi all,
I use MS Project Standard

I have several tasks and resources allocated and we have planned start and finish dates for the tasks.
I wanted to know how many person days are planned for a given time period for a given summary task (which may include 100s of tasks).
The summary task showed me the overall planned days for the entire time frame. I set a filter, starting date 1.7.2014 or later, end date 31.10.2014 or earlier and got the tasks which match this criteria. But the summary tasks working days did not change, so it still shoed the entire amount of effort in the summary task. How can I get the amount of planned working days just for the filtered tasks?
Thanks in advance
Bumpui