Master Project Weekly Summary Issue
Hi everyone,
I have a master project that combines several sub projects that contain identical sub tasks. When I review the master project by week, I only see the task names and not the parent task. As a result I end up with a series of 'tasks' that all have the same name making it impossible to figure out what the actual item refers to. Attached is a screen grab to hopefully clarify this. I guess the question is:
"How do I display the parent task for a summary view?"