Project 2013 - entering work hours at a monthly level
View Single Post
05-25-2014, 08:38 AM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
Your task ends on May 30 2014. Try entering a zero for the resource in May. When I recreated your scenario, entering the zero took care of the end date of the assignment. Testing using Project 2010 SP-2 and the April 2014 cumulative update.