Are the other teams documents in the project plan? If so, add a review task to the chain and assign the necessary resources. You may run in to an overallocation issue where R1 is scheduled to work on one of his/her documents and also review the output from the other team. You'll need to decide how to divide the labor requirement.

I also suggest looking into Deadlines on tasks to help alert you about slipping dates. Are you tracking the progress of the work as well?