Make tasks Duration automatically change with date changes
View Single Post
05-15-2014, 05:47 AM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
If the task really started when it was planned, set an actual start date and it will not move. I suggest tracking the project to supply actual data and then re-projecting the finish dates.