Sub-Project and resource report
View Single Post
04-26-2014, 08:27 AM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
Actually the Resource Group filter still works in Project 2010 - the Percent allocation rolls up to the group level. The resource group is resource field, while we are using Project as an assignment group.