Quote:
Originally Posted by JulieS View Post
What release of Project? What service pack do you have applied? Project 2007 is up to SP-3, Project 2010 is up to SP-2, and Project 2013 is up to SP-1.
It's Project 2007, SP1. I'll try and get IT to patch SP3 and see if that helps!

Quote:
Originally Posted by JulieS View Post
When you say you enter "data from .5 to 5 days per week for each task" - I assume you are entering work in the assignment row in the Resource Usage view? If you zoom in do you see the hours per day spread as expected? If I enter work per week - unless I am using Fixed Duration tasks, the task duration shortens when I enter 4 hours (.5 days) of work on a task in a week.
That's correct, i am entering work in the assignment row in the resource usage view. When i zoom in then i see the hrs spread as expected.

Quote:
Originally Posted by JulieS View Post
In testing with Project 2010 and manually entering the work on the assignment line - the weekly values match the default Baseline Work Visual Report.
That's interesting, if SP3 doesn't help then i'll try to get an upgrade to Project 2010.

Thanks again for your help Julie, much appreciated. Will keep the group posted on progress.