Quote:
Originally Posted by JulieS
What release of Project? What service pack do you have applied? Project 2007 is up to SP-3, Project 2010 is up to SP-2, and Project 2013 is up to SP-1.
|
It's Project 2007, SP1. I'll try and get IT to patch SP3 and see if that helps!
Quote:
Originally Posted by JulieS
When you say you enter "data from .5 to 5 days per week for each task" - I assume you are entering work in the assignment row in the Resource Usage view? If you zoom in do you see the hours per day spread as expected? If I enter work per week - unless I am using Fixed Duration tasks, the task duration shortens when I enter 4 hours (.5 days) of work on a task in a week.
|
That's correct, i am entering work in the assignment row in the resource usage view. When i zoom in then i see the hrs spread as expected.
Quote:
Originally Posted by JulieS
In testing with Project 2010 and manually entering the work on the assignment line - the weekly values match the default Baseline Work Visual Report.
|
That's interesting, if SP3 doesn't help then i'll try to get an upgrade to Project 2010.
Thanks again for your help Julie, much appreciated. Will keep the group posted on progress.