View Single Post
 
Old 04-24-2014, 12:29 PM
SusanK SusanK is offline Windows 7 32bit Office 2010 32bit
Novice
 
Join Date: Apr 2014
Posts: 5
SusanK is on a distinguished road
Default Display Activities by Day Number

Hello everyone,

Our executives have asked for a list of major project activities by day number. For example: If day 1 is January 15th (the start date of the project) and the next major activity is on January 20th, then that activity would fall on "Day 5".

Is there anyway to automatically have the day number calculated and displayed in the Gant chart (or a report)?

I've attached a manual example. See column "Day".

I hope I've explained this clearly.

Thank you.
Attached Files
File Type: pdf Example.pdf (161.2 KB, 20 views)
Reply With Quote