Quote:
Originally Posted by JulieS View Post
You'll need two custom groups:

For the Projects and Resource hours per project:

In the master file, apply the Task Usage view and create a group that groups by Project and then by Resource Name. Click the Check box for "group assignments not tasks" and select Assignments in the field type for the Resource Names row. Zoom out of the Task Usage view to show months.
...

Hello, I have a little questions.
Let's start with the first.
The method outlined works very well if I want to know how the resources are divided into several sub-projects.
Instead, if I want to see how the hours are divided into several sub-projects, the method has a bug.
Infact, this happens when the master file connects the sub-projects that in turn contain other sub-projects: if the master connects the sub-project 1 that contains not only some tasks but also another sub-project 1A, 1B, etc...then the proposed method can to see the hours of the programmed tasks but not those listed in the sub-1A and 1B.
How can I see all the hours contained in sub-projects of a master plan's sub-projects?