View Single Post
 
Old 03-06-2014, 12:10 PM
ketanco ketanco is offline Windows 7 64bit Office 2007
Expert
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default using a predecessor twice

it is not possible to use one task twice, for an activity's predecessor. lets say installation of drywall and taping tasks. I want to link taping as

drywall SS + 3 day

which i do, and it is fine

but

taping also can not finish, before drywall can finish. impossible. so, how to show this? MS project doesnt let me to also put a drywall FF as a predecessor to taping

i do not and can not end up with wrong schedule anyway, as my taping can not be complete before drywall is finsih so my dates are ok but as far as showing the relationships i am asking
Reply With Quote