Hi Julie
Unfortunately I cant share the file. However after further investigation I found one task that had the duration increased from 75 days to 84 days as a result of exporting to XLM and re-importing to a new plan. Once I fixed the duration the go-live returned to the original date.
As you, I have used this option many times before and have never seen this issue.
Thanks for your help.
Tony
|