Differentiate certain activities from hypotetical activities in gantt chart
View Single Post
02-24-2014, 10:47 AM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
You can use a Flag field (Flag1 for example) and set the uncertain tasks to "yes". You can then filter on the Flag field.