Formula To Calculate Countdown Days To Project Completion
View Single Post
02-19-2014, 11:15 AM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
Add a spare Duration column (Duration1 for example). Right click on the column heading and choose Custom Fields. Click the Formula button and enter the formula below:
ProjDateDiff([Finish],[Project Finish])