I'm hoping there is a way to do this without creating individual tasks.

Scenario:
  • Project 1: Test Cycle task = 2/10 - 2/14
  • Project 2: Test Cycle task = 2/17 - 2/28
  • Resource 1: Assigned to both projects
This week this resource needs to be allocated 100% to Project 1, 0% to Project 2. Starting next week this resource needs to be allocated 50/50 to each project. Is there a way to set this up without having to go in each week and manually change the allocations on the test cycle task?

Thanks!