Physical % Complete and Task Duration
View Single Post
02-09-2014, 09:21 AM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
If you wish Project to update actual and remaining duration and actual and remaining work, don't use Physical % complete. Use either % complete or % work complete.