View Single Post
 
Old 01-28-2014, 03:02 PM
JulieS JulieS is offline Windows 7 64bit Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Its a bit tough for my old eyes to see your Gantt chart view. I'm guessing you have items for each of the containers organized by summary task?

If you have coded each task with the container ID consider creating a custom group (by container ID) to see summary level % complete. Filtering does not recalculate the % complete only for visible tasks.

Post back if you need more guidance on setting up the group.
Reply With Quote