Yes. You should model the work in Project, entering tasks, durations, relationships, resources (as you are tracking work and cost). Then before you start supplying actual data - save a baseline. The original baseline data:baseline start, baseline finish, baseline work, baseline cost, baseline duration) will then not be changed by entering actuals. Project will calculate variance - work, cost, start, finish, and duration for you.
|