Default project for projected vs physical

Hi everyone! I'm new to the form and have searched for an answer to my question to no avail, so decided to post a questions for what I'm struggling with. I use MSP 2007, I have a simple schedule but I need to track/calculate planned vs actual and I don't want % complete to go back and change my "planned" units automatically. I included a sample I use in Excel now. Basically all tasks actual were either over or under planned, but all work is 100% complete. Is there anyway to pull this off using projects?

Thanks in advance!

See attached PDF. Thanks