Cross Project Dependencies
Hi Fellow Forum members
I am having an issues with cross-project dependencies.
..The settings in File/Options are correctly set.
..I have both project plans open and stored on my desktop
..I open the task information box for the Successor task and enter PROJECT1\2 in the ID box and tab across. The remaining boxes show External Task. I then click OK.
No external (grey) task appears in my plan and when I go back into the Task Information box the external predecessor has disappeared.
Any ideas on a resolution would be appreciated.
Thanks