Hi Julie
Yes they are Predecessor task numbers.
I have Project 2010 and Excel 2010.
I have tried formatting the cells in Excel to General BEFORE pasting the data from Excel but to no avail. Excel still tries to convert the Predecessor data.
When I do a "Save As" from Project to an Excel file it works perfectly. However as I have a template that I need to use to populate I need to be able to copy from Project then activate the Excel Workbook and then paste the data from A1.
Hope this makes it clear what I need.
Kind regards
Tony
|