Thread
: [Solved]
Manual Task End Date
View Single Post
12-16-2013, 08:02 AM
JulieS
Windows 7 64bit
Office 2010 32bit
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
I'm guessing you'd like a task end date to end after the Project Summary task? No, sorry. The finish date of the Project Summary task (should be row zero, not one) will be the latest date of all tasks (auto or manually scheduled) in the project.
JulieS
View Public Profile
Find all posts by JulieS