Thread
:
Assigning finish date to work with %complete
View Single Post
12-09-2013, 10:22 AM
JulieS
Windows 7 64bit
Office 2010 32bit
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
You may select individual tasks and use the Update Project - reschedule uncompleted work command (Project ribbon 2010 or Tools Tracking Updating Project in 2007) to split the task and move the remaining work to a new date.