The Start/stop are correct in that it shows numerically.
The software is not recognizing 24hrs per day and 168 hours per week, I think.
I have the timescale set up with the bottom tier at 2-12 increments, which indicates 2 shifts of 12 hours each for each calendar day. The middle tier shows 1 day increments
So when I want to schedule a task of 3 shifts or 36 hours, I want it and it should show a task bar the length of 3-12 segments or 1.5 calendar days.
I have the default time from 7:00am to 7:00pm for the day shift and 7:00pm to 7:00am for the 2nd or night shift. (I think)
I really do not want to develop a second schedule, one for the day shift and one for the night shift.
Thanks
|