Over-allocated resource - resource holiday
I have set up, on resource sheet, all of the resources to be used in my project plan. I have used the resource availability field to enter when users are on holiday (set units at 0% for the duration they are off, and back to 100% for their return).
Now, for example, a resource has been indicated as Project Manager resource for 1st November 2013 to 1st February 2014, but as they are on leave 1st - 7th December, they come up as being over-allocated as they are allocated as PM during the week they are off.
Is there any way I can get Project to ignore the period when their availability is set to 0%, or is there somewhere else I need to add their holidays in?
|