Default any way to exclude activity from critial path

hello
i have a scaffolding activity, which effects the start date of construction activities, by a SS relationship.

we are saying even after the construction activities finish, that scaffold will remain in place for a while. so, the scaffold end date is the latest. so the critical path automatically shows scaffolding. but i dont want that. i want to exclude the scaffolds form critical path calculation and critial path to calculate from the construction activities, even if they end earlier than scaffold end date.

can i exclude the scaffolding activities from critical path calculation, but still keeping the link between it and the construction activities?