I'm guessing you mean past its baseline finish? You could certainly apply a highlight filter looking for tasks with finish variance (assuming you have saved a baseline) that have % complete < 100%.
Another option is to use the Status Indicators. While they won't change background color, they will flag tasks that are late.
|