Default Finding Earned Values for Different Baselines in a single project

Hi,

If i have a project which has two or more baselines: say Baseline 1,2 & 3. How will i find out out the total earned value (BCWP) for the entire project (till date)?

Usually, we set Earned value calculations to Baseline (by default). But, as we re-baseline the schedule, we get newer planned values, like Baseline Cost 2, Baseline Cost 3. Now, if we need to find out earned value for the baseline 3, we need to set up Earned value calculation (Tools -> Options -> Calculation -> Earned Value -> Baseline 3. What is the solution.

Please help.
Thanks in advance.