Need totoal cost despite project being in progress
View Single Post
07-23-2013, 06:06 AM
JulieS
Windows 7 64bit
Office 2010 32bit
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
I'm afraid I'm not following.
You are correct the Cost field = Remaining + Actuals.
If you are not supply progress in Project (not recording Actuals) then doesn't the Cost = original cost?
JulieS