36 days task at 40% effort - only "0.86 days" in resource
View Single Post
07-09-2013, 06:32 AM
JulieS
Windows 7 64bit
Office 2010 32bit
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
What happens if you unassign bob and then re-assign? Assignments can certainly be edited in the Task or Resource usage view - do you see a pencil in the indicator column to the left of the assignment?