Thread
: [Solved]
36 days task at 40% effort - only "0.86 days" in resource
View Single Post
07-09-2013, 06:16 AM
hanvyj
Windows XP
Office 2010 32bit
Advanced Beginner
Join Date: Feb 2012
Posts: 33
I've checked working time calendar, the only non-working time is the weekends. I'm not sure what you mean by resource leveled? I certainly haven't tried to do it :S
hanvyj
View Public Profile
Find all posts by hanvyj