I'm just using one project file. I've created the programme of work much like a normal project - just a very high level one.
So I have things like:
STREAM OF WORK
-Project A
--information architecture (resource assigned here)
(times a bunch of these)
But when I go into team planner instead of seeing "Project A - information architecture" against a resource it just shows "information architecture". So I can't see at a glance what project is actually relates to.
Is there a way to improve the task detail?
|