View Single Post
 
Old 06-19-2013, 02:27 AM
Evgeny Evgeny is offline Windows 7 64bit Office 2007
Novice
 
Join Date: Dec 2012
Posts: 3
Evgeny is on a distinguished road
Default How to bring in one view task and resource fields?

Dear all,
I wonder it is possible to create a view, where I will bring both task and resource fields together?
If I assign resource to a task, I can then either go to task usage view, and then I will be able to insert columns with task fields or I can go to a resource usage and I will be able to show resource fields, but I need to have a view, where I would have possibility to show both types of fields. So in a way I would like to have an assignment table.
Specifically I would like to have a view, where for s specific assignment I would show Text1 field of a Task as well as Text1 field of a resource.
Is it possible?
Regards.
Evgeny
Reply With Quote