Thread
:
Subtasks
View Single Post
06-11-2013, 05:53 AM
JulieS
Windows 7 64bit
Office 2010 32bit
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
I'm not a coder but I would set the Outline Level property of the task versus just indenting. Or, you'll need to stop the OutlineIndent after the first inserted task - assuming all tasks after that are to be at the same outline level.
JulieS
View Public Profile
Find all posts by JulieS