OK, so I went and set all the subcontractors to 10 in the Max units box. 1 is the default, I assume that corresponds to 100%, So I have set all my sub’s at 1000%, this should be a overkill but I do not want the program to make any adjustments because of this issue. This has removed all the over-allocation flags.
Concerning the automatic leveling, this would be on the resource ribbon tab, level section, leveling options, I see a radio button selection for leveling calculations, manual was and is selected.
This seems to have fixed this issue, Thanks... Moving on to updating and extracting a short interval schedule out of the main schedule, likely will post again
|